Stage 1, Section 1
- Surveys and investigations: July - August 2021
- Public consultation: 8 September 2021 - 22 September 2021
- Tender advertised: October 2021
- Work started: Monday, 22 August 2022
- Work completed: 2024
Stage 1, Section 2
- Surveys and investigations: February 2022 and again in late 2023.
- Public consultation: March/April 2024 and August – September 2022
- Tender advertised: late 2024
- Construction start: early 2025
- Construction completion: mid 2026
We will update road users and the community about the approach for construction.
Stage 2
- Designs started in late 2022.